Plan A’s Key Responsibilities
- Plan A were asked to provide management structure and rigour for the Design Team.
- We prepared a detailed design programme for all packages coordinated with the contractor’s programme.
- We took over the existing self-regulating change management procedures and managed the process on behalf of the Client.
- Project: The Factory, Manchester, UK
- Sector: Culture
- Architect: OMA
- Client: Manchester International Festival
- Structural Engineering & Facades: Buro Happold
- Civil Engineering: BDP
- Size: 30,000 sqm
- Plan A Appointed: Stage 5